    PracticeACCAACCA BT — Business & Technology Practice Exam 4Question 50
    Hard4 marksMultiple Choice
    Syllabus D: Leadership and managementSyllabus DLeadershipMotivationMTQ

    ACCA · Question 50 · Syllabus D: Leadership and management

    Section B (Syllabus D)

    Scenario: 'Project Horizon' is a failing public infrastructure project. The team is severely demotivated, missing deadlines, and constantly arguing. A new Project Director, Sarah, is appointed. She immediately implements a strict autocratic leadership style to force compliance and hit short-term deadlines. She also introduces a piece-rate bonus system (more money for faster work) based on Taylor's scientific management principles. However, she ignores the team's complaints about unsafe working conditions.

    Based on the scenario and your knowledge of leadership and management (Syllabus D), select the FOUR correct statements.

    Answer options:

    A.

    Sarah's autocratic style aligns with McGregor's Theory X view of management, assuming workers need to be controlled and coerced.

    B.

    According to Maslow, ignoring unsafe working conditions means the team's basic Safety needs are not being met, preventing higher-level motivation.

    C.

    The piece-rate bonus system relies on the assumption that employees are primarily motivated by financial reward (Economic Man theory).

    D.

    In the Blake and Mouton Managerial Grid, Sarah is currently exhibiting a 'Task Management' (9,1) style.

    E.

    Sarah's approach perfectly balances Adair's three circles: Task, Team, and Individual.

    F.

    According to Herzberg, the piece-rate bonus will act as a powerful long-term Motivator factor.

    How to approach this question

    Map Sarah's actions to the theories: Autocratic = Theory X. Ignoring safety = Maslow's safety needs. Piece-rate = Taylor/Economic Man. High task/low people = Blake & Mouton Task Management.

    Full Answer

    This MTQ covers McGregor, Maslow, Taylor, and Blake & Mouton. Sarah's autocratic, money-driven, safety-ignoring approach perfectly illustrates Theory X, failure to meet Maslow's safety needs, Taylor's economic man, and a 9,1 Task Management style. Statement E is wrong because she ignores Team/Individual. Statement F is wrong because Herzberg views pay as a hygiene factor.

    Common mistakes

    Believing that a bonus system is a 'Motivator' under Herzberg's specific theory.
    Question 49All questionsQuestion 51

    Practice the full ACCA BT — Business & Technology Practice Exam 4

    52 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01Section A AstroDyne is a commercial space-tech startup developing low-earth orbit satellite depl...MediumQ02Section A Titanium Forge, a heavy manufacturing plant, is planning a massive expansion that will...EasyQ03Section A Verdant Retreats operates ultra-luxury eco-lodges in remote rainforests. They recently...MediumQ04Section A GhostBites operates a network of 'cloud kitchens' (delivery-only food preparation faci...MediumQ05Section A GreenYield is an agricultural organization owned entirely by the farmers who supply ra...Easy
    View all 52 questions →