Easy2 marksMultiple Choice
Standard costingLabor VariancesSyllabus E

ACCA · Question 28 · Standard costing

A remote software development team has a standard labor rate of $40 per hour. During the week, they were paid for 500 hours, but due to a server outage, 50 hours were recorded as idle time.

What is the idle time variance?

Answer options:

A.

$2,000 Favorable

B.

$2,000 Adverse

C.

$18,000 Adverse

D.

$0

How to approach this question

Idle time variance is simply the idle hours multiplied by the standard labor rate. It is always adverse.

Full Answer

B.$2,000 Adverse✓ Correct
Idle time variance represents the cost of paying workers when they cannot work. Variance = 50 idle hours * $40 standard rate = $2,000. Since money was paid for no output, it is Adverse.

Common mistakes

Trying to calculate efficiency variance instead of idle time variance.

Practice the full ACCA MA — Management Accounting Practice Exam 2

38 questions · hints · full answers · grading

More questions from this exam