Medium2 marksMultiple Choice
Cost Behavior and ClassificationSyllabus ACost Classification

ACCA · Question 02 · Cost Behavior and Classification

Section A

Quantum AI, a tech startup, classifies its costs to better understand cost behavior. Server hosting costs are charged at a flat rate of $5,000 per month for up to 10 terabytes of data processed. For every additional terabyte processed, an extra $400 is charged. How should this cost be classified?

Answer options:

A.

Stepped fixed cost

B.

Semi-variable cost

C.

Variable cost

D.

Fixed cost

How to approach this question

Analyze the cost structure: it has a base flat fee (fixed) and an additional per-unit charge (variable). This combination defines a semi-variable cost.

Full Answer

B.Semi-variable cost✓ Correct
Semi-variable costs (or mixed costs) contain both a fixed element (the $5,000 flat rate) and a variable element (the $400 per additional terabyte).

Common mistakes

Confusing semi-variable with stepped fixed costs. Stepped fixed costs jump in blocks, whereas semi-variable increases continuously after the fixed threshold.