ACCA · Question 03 · A. The nature, source and purpose of management information
An offshore wind farm incurs a maintenance cost that remains constant up to 50 turbine inspections per month. If more than 50 inspections are required, an additional specialized crew must be hired, causing the total maintenance cost to jump to a higher flat rate up to 100 inspections.
How should this cost be classified?
Answer options:
Variable cost
Semi-variable cost
Stepped fixed cost
Curvilinear cost