Medium1 markMultiple Choice
Domain 4.3: Migration StrategyMigrationSnowballData Transfer

AWS SAP-C02 · Question 42 · Domain 4.3: Migration Strategy

An enterprise is planning a massive migration of 10 PB of data from an on-premises SAN to Amazon S3. They have a 1 Gbps internet connection. They need to complete the migration within one month. What is the MOST feasible migration strategy?

Answer options:

A.

Use AWS DataSync over the 1 Gbps internet connection.

B.

Establish a 10 Gbps AWS Direct Connect and use AWS DataSync.

C.

Order multiple AWS Snowball Edge Storage Optimized devices to transfer the data offline.

D.

Use AWS Storage Gateway Volume Gateway to cache the data to S3.

How to approach this question

Calculate transfer times or recognize petabyte-scale offline transfer tools.

Full Answer

C.Order multiple AWS Snowball Edge Storage Optimized devices to transfer the data offline.✓ Correct
Order multiple AWS Snowball Edge Storage Optimized devices to transfer the data offline.
For petabyte-scale data transfers where network bandwidth is insufficient (10 PB over 1 Gbps takes years), offline transfer using the AWS Snow Family (Snowball Edge or Snowmobile) is the only feasible solution.

Common mistakes

Overestimating network transfer speeds for petabyte-scale data.