Hard1 markMultiple Choice
Area III: Select Transactionspercentage of completionASC 606construction contractsrevenue recognition

CPA · Question 27 · Area III: Select Transactions

Riverside Corp. enters into a contract to construct a building for $3,000,000. The contract is expected to take 3 years to complete. At the end of Year 1:<br/>- Costs incurred to date: $900,000<br/>- Estimated costs to complete: $1,800,000<br/>- Billings to customer: $800,000<br/>- Cash collected: $750,000<br/><br/>Using the percentage-of-completion method, how much revenue should Riverside recognize in Year 1?

Answer options:

A.

$800,000

B.

$900,000

C.

$1,000,000

D.

$750,000

How to approach this question

Calculate percentage complete as costs incurred to date divided by total estimated costs (incurred + estimated to complete). Multiply this percentage by total contract price to determine cumulative revenue to be recognized.

Full Answer

C.$1,000,000✓ Correct
$1,000,000
Under ASC 606 (and previously ASC 605-35), percentage-of-completion method recognizes revenue based on progress toward completion. Progress = $900,000 ÷ ($900,000 + $1,800,000) = 33.33%. Revenue = $3,000,000 × 33.33% = $1,000,000. This method matches revenue with the progress of work performed.

Common mistakes

Using billings or cash collections for revenue recognition, not including estimated costs to complete in total costs, or applying percentage to costs instead of contract price

Practice the full CPA FAR Practice Exam 2

50 questions · hints · full answers · grading

More questions from this exam