Medium1 markMultiple Choice
CPA · Question 22 · Area I: Information Systems
A company uses an 'Incremental' backup strategy. A full backup is performed on Sunday. Incremental backups are performed Monday through Saturday. If the system crashes on Thursday morning (before Thursday's backup), what is required to restore the system?
A company uses an 'Incremental' backup strategy. A full backup is performed on Sunday. Incremental backups are performed Monday through Saturday. If the system crashes on Thursday morning (before Thursday's backup), what is required to restore the system?
Answer options:
A.
Sunday Full + Wednesday Incremental
B.
Sunday Full + Wednesday Differential
C.
Sunday Full + Monday Incremental + Tuesday Incremental + Wednesday Incremental
D.
Wednesday Incremental only
How to approach this question
Understand the chain dependency of Incremental backups.
Full Answer
C.Sunday Full + Monday Incremental + Tuesday Incremental + Wednesday Incremental✓ Correct
C
Incremental backups save only the data changed since the *last* backup (whether full or incremental). To restore, you need the last Full backup and *every* subsequent incremental backup in order up to the point of failure.
Common mistakes
Confusing Incremental (needs chain) with Differential (needs only last Full + last Differential).
Practice the full CPA ISC Practice Exam 3
82 questions · hints · full answers · grading
More questions from this exam
Q01A CPA is advising a client who is migrating their legacy on-premise ERP system to a cloud-based s...MediumQ02During a review of a client's cloud governance structure, an auditor notes that the client uses a...MediumQ03An auditor is evaluating the 'Processing Integrity' principle for a financial institution's loan ...HardQ04A company uses a batch processing system to update inventory records overnight. The 'Grandfather-...HardQ05During a walkthrough of the change management process, an auditor observes that the 'Developer' r...Medium
Expert