Medium1 markMultiple Choice

GCP PCA · Question 01 · Domain 1: Designing and Planning a Cloud Solution Architecture

CASE STUDY: TechStream Gaming. 500 emp, $100M rev. On-prem US/EU, 200 servers, MySQL 5TB. 2M peak users. $100K/mo cost. Req: Cut cost 40%, 5x growth, 3 new regions, daily deploys. CEO: Scale fast. CFO: <$100K/mo, 18mo ROI. CTO: Low cloud skills, 99.95% uptime. Tech: <100ms latency, real-time analytics, 5x spikes, EU data residency, DDoS protection, CI/CD. Constraints: 12mo migration, 4hr downtime, 20 devs (Java/MySQL), 5 ops (no cloud), $2M budget.

Which migration strategy should you recommend for the legacy monolithic application to meet the 12-month timeline and team skill constraints?

Answer options:

A.

Refactor entirely to microservices on GKE before migrating.

B.

Rehost to Compute Engine using Migrate for Compute Engine.

C.

Replatform to Cloud Run by containerizing the monolith.

D.

Replace with a SaaS gaming platform.

How to approach this question

Evaluate constraints: 12 months, low cloud skills.

Full Answer

B.Rehost to Compute Engine using Migrate for Compute Engine.✓ Correct
Rehosting (Lift and Shift) is the only viable strategy to move 200 servers in 12 months with a team lacking cloud skills.

Common mistakes

Choosing refactor because it's 'more cloud native', ignoring constraints.

Practice the full GCP Professional Cloud Architect Practice Exam 2