    PracticeACCAACCA BT — Business & Technology Practice Exam 1Question 51
    Hard4 marksMultiple Choice
    Syllabus E: Personal effectiveness and communication in businessSection BSyllabus EMTQCommunication

    ACCA · Question 51 · Syllabus E: Personal effectiveness and communication in business

    SCENARIO: 'Virtual Solutions Ltd' has a remote team. A manager in London is trying to call a developer in Tokyo, but the developer is asleep. When they finally connect, they argue over a deadline. They resolve it by both giving up some of their demands to reach a middle ground. Suddenly, the main server crashes, and the manager must drop everything to fix it immediately. Later, the manager assigns a junior staff member to follow a senior developer around for a week to learn the job.

    Identify the correct terms:

    1. The communication barrier caused by the time difference.
    2. The conflict resolution style used (middle ground).
    3. The Eisenhower Matrix quadrant for the server crash.
    4. The competence development method used for the junior staff.

    Which option represents the correct combination?

    Answer options:

    A.

    1-Semantic barrier, 2-Collaborating, 3-Urgent but Not Important, 4-Mentoring

    B.

    1-Physical barrier, 2-Compromising, 3-Urgent and Important, 4-Shadowing

    C.

    1-Psychological barrier, 2-Accommodating, 3-Urgent and Important, 4-Coaching

    D.

    1-Physical barrier, 2-Compromising, 3-Important but Not Urgent, 4-Mentoring

    How to approach this question

    1. Time/distance = Physical. 2. Both give up something = Compromise. 3. Crisis = Urgent & Important. 4. Observing = Shadowing.

    Full Answer

    B.1-Physical barrier, 2-Compromising, 3-Urgent and Important, 4-Shadowing✓ Correct
    1. Timezones and geography are physical barriers to communication. 2. Compromising (Thomas-Kilmann model) involves both parties conceding something to reach a middle ground. 3. A server crash is a crisis, making it Urgent and Important (Quadrant 1). 4. Shadowing is a training method where a junior observes a senior working.

    Common mistakes

    Confusing Compromising (lose-lose/middle ground) with Collaborating (win-win).
    Question 50All questionsQuestion 52

    Practice the full ACCA BT — Business & Technology Practice Exam 1

    52 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A highly vocal but underfunded local community group is actively opposing the construction of a n...MediumQ02CloudNet Inc., a global data storage provider, is forced to restructure its server network due to...MediumQ03BioCure Ltd manufactures a highly specialized, patented drug for a rare genetic disorder. There a...EasyQ04In the context of Porter's Five Forces, which of the following scenarios best illustrates a high ...MediumQ05AgriGrow is an organization owned entirely by the farmers who supply it with raw wheat. The organ...Easy
    View all 52 questions →