ACCA · Question 01 · Essential elements of the legal system
A dispute has arisen between 'AquaHarvest Ltd' and a supplier over a £150,000 contract for specialized algae harvesting equipment. The supplier claims breach of contract.
In the English civil court system, which track and court of first instance will most likely handle this claim?
Answer options:
The fast track in the County Court.
The multi-track in the County Court.
The multi-track in the High Court.
The small claims track in the Magistrates' Court.
60 questions · hints · full answers · grading