ACCA · Question 06 · Decision-making techniques
Section A
Apex Consulting is deciding whether to accept a special one-off contract. The contract requires 500 hours of highly skilled labor. Apex currently has spare capacity of 200 hours for this labor grade. The remaining 300 hours would need to be diverted from an existing project that generates a contribution of $40 per hour. The skilled labor is paid a fixed weekly salary, and no overtime is possible.
What is the relevant cost of labor for this special contract?
Answer options:
$0
$8,000
$12,000
$20,000