    PracticeACCAACCA PM — Performance Management Practice Exam 4Question 12
    Medium2 marksShort Answer
    Budgeting and controlLearning CurveQuantitative AnalysisSection A

    ACCA · Question 12 · Budgeting and control

    Section A

    AeroParts Manufacturing is producing a complex new turbine component. The first unit took exactly 200 labor hours to produce. The production manager expects a 90% learning curve to apply to this process.

    Calculate the expected average time per unit for the first 4 units produced. (Enter the numerical value only)

    How to approach this question

    Use the tabular method for doubling output: 1 unit = 200 hours average. 2 units = 200 * 0.90 = 180 hours average. 4 units = 180 * 0.90 = 162 hours average.

    Full Answer

    Using the doubling rule for learning curves: Cumulative Units = 1, Cumulative Average Time = 200 hours. Cumulative Units = 2 (doubled), Cumulative Average Time = 200 x 0.90 = 180 hours. Cumulative Units = 4 (doubled again), Cumulative Average Time = 180 x 0.90 = 162 hours.

    Common mistakes

    Calculating the total time for 4 units (648 hours) instead of the average time, or applying the 90% only once.
    Question 11All questionsQuestion 13

    Practice the full ACCA PM — Performance Management Practice Exam 4

    32 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01**Section A** AgriCorp, a large-scale agricultural business, has recently implemented a system o...EasyQ02**Section A** GlobalHealth NGO operates in 15 developing countries, providing emergency medical ...MediumQ03**Section A** NovaTech is a startup developing a revolutionary AI-driven translation earpiece. M...MediumQ04**Section A** MetroWater, a public utility company, is transitioning from traditional absorption...EasyQ05**Section A** Titan Heavy Industries manufactures industrial cranes. The factory operates a bott...Medium
    View all 32 questions →