Hard1 markMultiple Choice
CPA · Question 24 · Area II: Technical Accounting
TechCorp is developing software for internal use. <br/>- Preliminary Project Stage costs: $50,000<br/>- Application Development Stage costs (coding, testing): $200,000<br/>- Data Conversion costs: $30,000<br/>- Training costs: $20,000<br/>- Post-implementation maintenance: $15,000<br/><br/>What amount should be capitalized as software assets?
TechCorp is developing software for internal use. <br/>- Preliminary Project Stage costs: $50,000<br/>- Application Development Stage costs (coding, testing): $200,000<br/>- Data Conversion costs: $30,000<br/>- Training costs: $20,000<br/>- Post-implementation maintenance: $15,000<br/><br/>What amount should be capitalized as software assets?
Answer options:
A.
$250,000
B.
$200,000
C.
$230,000
D.
$315,000
How to approach this question
Capitalize: Application Development (Design, Coding, Testing, Installation). Expense: Preliminary Project, Training, Data Conversion, Maintenance.
Full Answer
B.$200,000✓ Correct
B
ASC 350-40 requires capitalization only during the Application Development Stage. Preliminary costs ($50k), Training ($20k), Data Conversion ($30k), and Maintenance ($15k) are expensed.
Common mistakes
Capitalizing training or preliminary costs.
Practice the full CPA BAR Practice Exam 2
50 questions · hints · full answers · grading
More questions from this exam
Q01Orion Manufacturing provided the following data for the current year:<br/><br/>- Net Sales: $5,00...HardQ02A company has a Debt-to-Equity ratio of 1.5 and a Times Interest Earned (TIE) ratio of 4.0. The c...HardQ03An analyst is reviewing a company's quarterly revenue data using a visualization tool. The trend ...HardQ04TechSolutions Inc. reports Net Income of $500,000. The following items are included in the calcul...HardQ05A company is implementing a Balanced Scorecard. They have identified 'Employee Training Hours per...Hard
Expert