GCP PCA · Question 35 · Migration Plan
You are planning a massive data center migration to GCP involving 500 applications. You need to determine which applications to migrate first. What is the best practice for planning migration waves?
Answer options:
Migrate the most mission-critical applications first to prove the cloud works.
Migrate the databases first, then migrate the application servers months later.
Use StratoZone to map dependencies and migrate applications with the fewest dependencies first.
Migrate all 500 applications over a single weekend to minimize the transition period.