For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 03
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 03 · Task 1: Plan and manage project compliance

    A project manager discovers that a subcontractor has been disposing of chemical waste improperly, violating environmental regulations. The project is 85% complete and on the critical path. Replacing the subcontractor will cause a 2-month delay and a 20% budget overrun.<br/><br/>What is the BEST course of action for the project manager?

    Answer options:

    A.

    Allow the subcontractor to finish the remaining 15% of work under strict supervision to avoid project failure.

    B.

    Report the violation to the project sponsor and ask for guidance on whether to suspend the subcontractor.

    C.

    Suspend the subcontractor's work immediately and initiate a root cause analysis and remediation plan.

    D.

    Issue a formal warning to the subcontractor and deduct the cost of potential fines from their final payment.

    How to approach this question

    When facing legal/regulatory violations, the answer is always to stop the violation immediately. Schedule and cost impacts are secondary.

    Full Answer

    C.Suspend the subcontractor's work immediately and initiate a root cause analysis and remediation plan.✓ Correct
    C
    Compliance with legal and regulatory requirements is non-negotiable. The PM must stop the non-compliant activity immediately (Suspend work). Continuing the work (A) or just warning (D) exposes the organization to massive liability and violates ethical standards. Reporting (B) is part of the process, but the immediate action is to stop the violation.

    Common mistakes

    Prioritizing the project schedule (A) over legal compliance.
    Question 02All questionsQuestion 04

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...HardQ06During a compliance audit of a software project, the auditor identifies that the team is using op...Hard
    View all 60 questions →