Hard1 markMultiple Choice
Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

PMP · Question 06 · Task 1: Plan and manage project compliance

During a compliance audit of a software project, the auditor identifies that the team is using open-source code with a license that requires the final product to be open-source as well. This contradicts the company's proprietary business model. The code is deeply integrated into the architecture.<br/><br/>What is the MOST appropriate immediate action for the project manager?

Answer options:

A.

Ignore the finding as the code is already integrated and rewriting it is too expensive.

B.

Log the issue in the risk register and analyze the cost/schedule impact of replacing the code.

C.

Immediately fire the lead developer responsible for selecting the library.

D.

Purchase a commercial license for the open-source library to resolve the issue.

How to approach this question

Identify the problem (Legal/IP risk). PM action is to Assess/Analyze/Document before acting.

Full Answer

B.Log the issue in the risk register and analyze the cost/schedule impact of replacing the code.✓ Correct
B
This is a significant legal compliance threat (IP infringement/Business model conflict). The PM must first log it as a risk/issue and analyze the impact (re-work costs vs. legal exposure) to inform management decision-making. Ignoring it (A) is fatal. Firing (C) is reactive. Purchasing (D) might not be possible depending on the specific license.

Common mistakes

Assuming a commercial solution exists (D) or ignoring it due to sunk costs (A).