PMP · Question 07 · Task 1: Plan and manage project compliance

A project manager is preparing for a quality audit to ensure compliance with internal organizational standards. The project is using a hybrid approach.<br/><br/>Which TWO methods should the project manager use to support compliance? (Select TWO)

Answer options:

A.

Regularly review the quality management plan and compliance checklists.

B.

Wait for the external auditor to identify gaps before taking action.

C.

Focus exclusively on product functionality and ignore documentation.

D.

Conduct internal mock audits or peer reviews prior to the official audit.

E.

Delegate all compliance responsibilities to the legal department.

F.

Remove non-compliant features from the scope without change control.

How to approach this question

Look for PROACTIVE actions. Reviewing plans and conducting mock audits are proactive.

Full Answer

A, D
To support compliance, the PM should be proactive. Reviewing the plan (A) ensures the team knows the targets. Conducting mock audits (D) helps catch issues early. Waiting (B) or delegating entirely (E) are poor management practices.

Common mistakes

Thinking compliance is solely Legal's job (E).