For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 07
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 07 · Task 1: Plan and manage project compliance

    A project manager is preparing for a quality audit to ensure compliance with internal organizational standards. The project is using a hybrid approach.<br/><br/>Which TWO methods should the project manager use to support compliance? (Select TWO)

    Answer options:

    A.

    Regularly review the quality management plan and compliance checklists.

    B.

    Wait for the external auditor to identify gaps before taking action.

    C.

    Focus exclusively on product functionality and ignore documentation.

    D.

    Conduct internal mock audits or peer reviews prior to the official audit.

    E.

    Delegate all compliance responsibilities to the legal department.

    F.

    Remove non-compliant features from the scope without change control.

    How to approach this question

    Look for PROACTIVE actions. Reviewing plans and conducting mock audits are proactive.

    Full Answer

    To support compliance, the PM should be proactive. Reviewing the plan (A) ensures the team knows the targets. Conducting mock audits (D) helps catch issues early. Waiting (B) or delegating entirely (E) are poor management practices.

    Common mistakes

    Thinking compliance is solely Legal's job (E).
    Question 06All questionsQuestion 08

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →