    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 08
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 08 · Task 1: Plan and manage project compliance

    A project manager is leading a project to implement a new AI recruiting tool. A stakeholder raises a concern that the AI model might inadvertently discriminate against certain demographics, violating Equal Employment Opportunity (EEO) laws. The model has already been trained.<br/><br/>What is the BEST way for the project manager to address this compliance threat?

    Answer options:

    A.

    Proceed with the launch and monitor for complaints during the first month.

    B.

    Add a disclaimer that the tool is in beta and results should be verified manually.

    C.

    Commission an independent bias audit of the algorithm before release.

    D.

    Ask the development team if they used a diverse dataset for training.

    How to approach this question

    The threat is 'Potential Discrimination/Legal Violation'. The response must be 'Verify/Audit' to confirm the threat before acting.

    Full Answer

    C.Commission an independent bias audit of the algorithm before release.✓ Correct
    C
    When a specific compliance threat (bias/discrimination) is identified, the PM must determine the validity of the threat. An independent bias audit (C) provides the necessary data to decide whether the tool is legally safe to deploy. Proceeding (A) is reckless.

    Common mistakes

    Choosing A (monitor in production) which is too late for legal compliance.
    Question 07All questionsQuestion 09

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →