Hard1 markShort Answer
Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

PMP · Question 09 · Task 1: Plan and manage project compliance

A project manager is reviewing the project's adherence to regulatory requirements. The team conducts a formal examination of project deliverables and processes to verify they meet the specified compliance standards. What is the specific term for this formal examination?

How to approach this question

Provide the specific PMBOK/industry term. One word.

Full Answer

Audit
An audit is a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.

Common mistakes

Confusing 'Inspection' (checking a deliverable) with 'Audit' (checking the process/compliance).