Hard1 markShort Answer
PMP · Question 09 · Task 1: Plan and manage project compliance
A project manager is reviewing the project's adherence to regulatory requirements. The team conducts a formal examination of project deliverables and processes to verify they meet the specified compliance standards. What is the specific term for this formal examination?
A project manager is reviewing the project's adherence to regulatory requirements. The team conducts a formal examination of project deliverables and processes to verify they meet the specified compliance standards. What is the specific term for this formal examination?
How to approach this question
Provide the specific PMBOK/industry term. One word.
Full Answer
Audit
An audit is a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.
Common mistakes
Confusing 'Inspection' (checking a deliverable) with 'Audit' (checking the process/compliance).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard