    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 21
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valueBusiness EnvironmentValueTask 2

    PMP · Question 21 · Task 2: Evaluate and deliver project benefits and value

    A project manager is creating a Benefits Management Plan. <br/><br/>Which of the following components MUST be included to ensure accountability?

    Answer options:

    A.

    The Work Breakdown Structure (WBS)

    B.

    The detailed project schedule

    C.

    The name of the Benefit Owner

    D.

    The project team roster

    How to approach this question

    The question asks for 'Accountability'. Accountability = A Person/Owner.

    Full Answer

    C.The name of the Benefit Owner✓ Correct
    C
    A Benefits Management Plan must define *who* is responsible for monitoring and realizing the benefits. This is the 'Benefit Owner'. Without an owner, there is no accountability.

    Common mistakes

    Including project artifacts (WBS, Schedule) in the Benefits Plan.
    Question 20All questionsQuestion 22

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard