Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3Matching Conversion
PMP · Question 35 · Task 3: Evaluate and address external business environment changes
A project manager is monitoring the external environment and notes a significant drop in the currency exchange rate relevant to the project's imported materials. <br/><br/>Which project document should be updated FIRST?
A project manager is monitoring the external environment and notes a significant drop in the currency exchange rate relevant to the project's imported materials. <br/><br/>Which project document should be updated FIRST?
Answer options:
A.
Stakeholder Register
B.
Project Schedule
C.
Quality Management Plan
D.
Cost Baseline or Risk Register
How to approach this question
Link the Event (Currency Drop) to the Impact (Cost).
Full Answer
D.Cost Baseline or Risk Register✓ Correct
D
Economic changes like currency fluctuation impact project costs. The PM should update the Risk Register (if it's a new threat) or the Cost Baseline (via change control if the impact is realized).
Common mistakes
Updating the schedule (B) when the primary impact is cost.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert