PMP · Question 37 · Task 3: Evaluate and address external business environment changes
A project relies on a supply chain that passes through a region experiencing sudden geopolitical instability. <br/><br/>What is the BEST proactive step for the project manager?
Answer options:
Wait for a disruption to occur before acting.
Immediately switch suppliers to a more expensive local option.
Conduct a risk assessment of the supply chain and identify alternative sourcing options.
Increase the project budget to cover potential losses.