A project manager identifies that a new technology has emerged that could automate 30% of the project's scope, reducing cost but requiring a change in the team's skillset. The project is 20% complete.<br/><br/>What is the BEST approach?
A project manager identifies that a new technology has emerged that could automate 30% of the project's scope, reducing cost but requiring a change in the team's skillset. The project is 20% complete.<br/><br/>What is the BEST approach?
Answer options:
A.
Ignore the new technology to avoid scope creep.
B.
Perform a cost-benefit analysis of adopting the technology versus continuing as planned.
C.
Adopt the technology immediately to demonstrate innovation.
D.
Replace the current team with new experts.
How to approach this question
New Tech = Opportunity. Opportunity -> Analyze Cost/Benefit -> Decide.
Full Answer
B.Perform a cost-benefit analysis of adopting the technology versus continuing as planned.✓ Correct
B
External technological changes can offer opportunities. The PM should not ignore them (A) nor adopt blindly (C). A Cost-Benefit Analysis (B) determines if the change adds value to the business.
Common mistakes
Viewing all changes as 'Scope Creep' (A). Controlled change is good.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert