PMP · Question 45 · Task 3: Evaluate and address external business environment changes
A startup is developing a travel app. A global pandemic halts all travel. The project manager and sponsor meet to discuss the project's future. <br/><br/>Which decision represents a 'Pivot'?
Answer options:
Pause the project until travel resumes.
Cancel the project and disband the team.
Change the scope to develop a virtual tourism experience instead of booking physical travel.
Continue developing the booking engine as planned.