For IndividualsFor Educators
    ExpertMinds LogoExpertMinds
    HomePMPCheat Sheet
    Cheat SheetProject Management Institute (PMI)PMP

    PMP Exam Cheat Sheet: Formulas, Domains, and Key Concepts

    The essential reference for PMP candidates — earned value formulas, the three domains, agile vs predictive triggers, and the ITTOs most likely to appear on the 2024 ECO exam.

    ExpertMinds Editorial·21 January 2026·7 min read
    Take the PMP practice exams →

    The PMP exam (current ECO, since January 2021) is 180 questions in 230 minutes. Approximately 50% of questions are agile or hybrid. The exam does not reward memorising processes — it rewards understanding why a project manager would take a specific action. This cheat sheet focuses on concepts and formulas that distinguish right from wrong answers.

    Key fact:180 questions · 230 minutes · No published passing score. Results reported as Above Target / Target / Below Target per domain. PMI recommends "Target" or above in all three.

    The Three Domains

    DomainExam weightCore theme
    People42%Leading teams, managing stakeholders, resolving conflict, building a collaborative environment
    Process50%Executing projects — scope, schedule, cost, risk, quality, procurement — in predictive and agile contexts
    Business Environment8%Benefits realisation, compliance, org change management, external factors affecting the project
    Tip:Domain weighting means Process has the most questions, but People questions are where most candidates lose marks. They require judgment, not recall.

    Earned Value Formulas

    Term / FormulaDefinitionWhat it tells you
    PV (Planned Value)Budget authorised for scheduled workWhat you planned to spend by now
    EV (Earned Value)Budget authorised for work actually completedWhat you've earned for work done
    AC (Actual Cost)Cost actually incurredWhat you've spent
    SV = EV − PVSchedule VariancePositive = ahead; Negative = behind
    CV = EV − ACCost VariancePositive = under budget; Negative = over budget
    SPI = EV / PVSchedule Performance Index>1 = ahead; <1 = behind
    CPI = EV / ACCost Performance Index>1 = under budget; <1 = over budget
    EAC = BAC / CPIEstimate at Completion (if current CPI continues)What the project will cost at completion
    EAC = AC + ETCEstimate at Completion (with new estimate)Actual spent + new estimate to complete
    ETC = EAC − ACEstimate to CompleteCost remaining to finish
    VAC = BAC − EACVariance at CompletionProjected over/under budget at end
    TCPI = (BAC − EV) / (BAC − AC)To-Complete Performance IndexCPI needed to finish within original budget
    Key fact:Memory trick for SV and CV: always EV minus the other one. "Earned" is always first. SV = EV−PV. CV = EV−AC.

    Agile vs Predictive — Reading the Question

    Trigger phrase in questionLikely approach
    "requirements are unclear or likely to change"Agile / iterative
    "customer wants early and frequent delivery"Agile
    "self-organising team"Agile
    "regulatory compliance", "fixed requirements"Predictive / waterfall
    "contract with fixed scope and price"Predictive
    "some parts uncertain, some fixed"Hybrid
    "retrospective"Agile (Scrum)
    "lessons learned"Predictive (PMI traditional)
    "sprint", "velocity", "backlog"Scrum / agile
    "WBS", "baseline", "change control board"Predictive

    Test yourself on PMP

    Practice questions graded with detailed guidance.

    Sign up freePractice now →

    Conflict Resolution — Order of Preference

    1. Collaborating / Problem Solving — address root cause, best for PMI exams
    2. Compromising — both parties give something up
    3. Smoothing / Accommodating — emphasise agreement, de-emphasise differences
    4. Forcing — one party imposes their position
    5. Withdrawal / Avoiding — delay or retreat (worst option on PMI exams)
    Tip:On PMP exam questions about conflict: the answer is almost always "collaborate and problem-solve." Forcing and avoidance are almost always wrong.

    Power / Interest Grid — Stakeholder Engagement

    PowerInterestStrategy
    HighHighManage closely — key stakeholders
    HighLowKeep satisfied — don't overload with detail
    LowHighKeep informed — engaged but limited influence
    LowLowMonitor — minimum effort

    Risk Response Strategies

    StrategyFor threats or opportunities?What it means
    Avoid (threats) / Exploit (opportunities)BothChange plan to eliminate threat / ensure opportunity occurs
    Transfer (threats) / Share (opportunities)BothShift impact to third party (insurance, contracts)
    Mitigate (threats) / Enhance (opportunities)BothReduce probability or impact
    AcceptBothAcknowledge risk, no action (active = contingency plan; passive = deal with it if it happens)
    EscalateBothRisk is outside project scope — pass to programme or portfolio level

    Test your PMP knowledge

    Reading formulas is not the same as applying them under pressure. Practice PMP scenario questions to see how these concepts appear on the real exam.

    Sign up freePractice now →

    Leadership Styles — Quick Reference

    StyleWhen to usePMI preference?
    Servant LeadershipAgile teams — PM serves the team, removes blockersYes — strongly preferred for agile contexts
    Laissez-faireHighly experienced, self-directed expertsSituational — not the default
    TransactionalClear deliverables, reward/punishment structureAcceptable for predictive
    TransformationalLeading change, inspiring visionYes — for driving change
    Authoritative / DirectingCrisis, new team members, or when clarity is needed fastSituational

    Ready to Practice the full PMP?

    Graded results, exam simulation, and detailed guidance on every question.

    Sign up freePractice now

    About this exam

    180 questions · 230 minutes · no published pass mark
    Pass mark: Above Target on each domain

    Quick links

    Practice examsBrowse topicsOfficial exam page

    Exam topics

    People Domain42%Process Domain50%Business Environment Domain8%

    Related reading

    Why PMP Candidates Fail (And What to Do Differently)

    6 min read

    Agile vs Predictive PMP Questions: How to Read What They're Actually Asking

    5 min read

    PMP Exam Changes on 9 July 2026 — Everything Candidates Need to Know

    3 min read

    PMBOK 8th Edition Is Here: 6 Principles Replace 12, and Governance Gets Its Own Domain

    4 min read

    PMI Pulse 2025: Only 18% of Project Managers Have High Business Acumen — and the Exam Knows It

    3 min read

    Should You Take the PMP Before July 2026 or After? A Decision Framework

    5 min read

    Business Environment Is Now 26% of the PMP — How to Actually Study for It

    6 min read

    Power Skills vs Business Acumen: Where PMP Candidates Are Failing in 2026

    5 min read

    PMP Stakeholder Engagement Question Walkthrough (People Domain)

    6 min read

    PMP Business Environment Question Walkthrough (The New 26% Domain)

    6 min read

    ExpertMinds

    Ace your certifications with Practice Exams and AI assistance.

    • Browse Exams
    • For Educators
    • Blog
    • Privacy Policy
    • Terms of Service
    • Cookie Policy
    • Support
    • AWS SAA Exam Prep
    • PMI PMP Exam Prep
    • CPA Exam Prep
    • GCP PCA Exam Prep

    © 2026 TinyHive Labs. Company number 16262776.