Hard1 markMultiple Choice
Task 7: Address and remove impediments, obstacles, and blockers for the teamimpediment removalservant leadershipproblem solvingagile

PMP · Question 04 · Task 7: Address and remove impediments, obstacles, and blockers for the team

During sprint planning for a software development project, the development team reports that they cannot access the required third-party API for testing because the vendor's test environment is down indefinitely. This is blocking progress on three critical user stories. What should the project manager do FIRST?

Answer options:

A.

Document the impediment in the project risk register and inform the product owner

B.

Work with the team to identify alternative testing approaches or mock services that can unblock the work

C.

Escalate to senior management to pressure the vendor to restore their test environment

D.

Move the affected user stories to the next sprint and select different work for the current sprint

How to approach this question

Look for the option that actively removes impediments rather than just documenting or avoiding them. Servant leaders work with the team to find solutions.

Full Answer

B.Work with the team to identify alternative testing approaches or mock services that can unblock the work✓ Correct
B
Servant leaders actively work to remove impediments and blockers. Finding alternative solutions keeps the team productive while addressing the root issue.

Common mistakes

Choosing passive approaches like documentation or avoidance instead of active impediment removal. Remember that servant leaders are proactive problem solvers.