PMP · Question 12 · Task 1: Plan and manage project compliance
A project manager is reviewing the project's risk report. A risk regarding 'Potential non-compliance with new accessibility standards' has a high probability and high impact. <br/><br/>Which response strategy is BEST suited for this compliance risk?
Answer options:
Accept
Mitigate
Transfer
Exploit
60 questions · hints · full answers · grading