    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 13
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 13 · Task 1: Plan and manage project compliance

    A project manager is leading a project to launch a new pharmaceutical drug. The project has successfully passed all clinical trials (Quality requirements) but has not yet received final approval from the regulatory body. The marketing director wants to launch the advertising campaign immediately to capture market share.<br/><br/>What should the project manager do?

    Answer options:

    A.

    Allow the campaign to launch but include a disclaimer that approval is pending.

    B.

    Launch the campaign in regions where regulations are less strict.

    C.

    Use the contingency reserve to pay for any potential fines from early marketing.

    D.

    Advise the marketing director that the launch must wait until regulatory approval is confirmed.

    How to approach this question

    Prioritize Compliance over Business Pressure. Regulatory approval is a 'Finish-to-Start' constraint for Launch.

    Full Answer

    D.Advise the marketing director that the launch must wait until regulatory approval is confirmed.✓ Correct
    In the pharmaceutical industry, regulatory approval is a mandatory dependency for marketing and sales. Launching early violates compliance and risks the entire company's license. The PM must enforce this constraint despite business pressure.

    Common mistakes

    Bending to business pressure (A) or misusing reserves (C).
    Question 12All questionsQuestion 14

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard