PMP · Question 14 · Task 1: Plan and manage project compliance
A project manager needs to measure the extent to which the project is in compliance with safety regulations. <br/><br/>Which metric would be the MOST effective leading indicator of safety compliance?
A project manager needs to measure the extent to which the project is in compliance with safety regulations. <br/><br/>Which metric would be the MOST effective leading indicator of safety compliance?
Answer options:
A.
Total number of accidents reported last month
B.
Percentage of staff who have completed mandatory safety training
C.
Cost of fines paid for safety violations
D.
Number of days since the last accident
How to approach this question
Distinguish between Leading (predictive) and Lagging (historical) indicators. Training happens *before* work, making it leading.
Full Answer
B.Percentage of staff who have completed mandatory safety training✓ Correct
B
Leading indicators help predict future performance. Staff training completion (B) indicates the team's readiness to work safely. Accidents (A), fines (C), and days since accident (D) are lagging indicators—they tell you what already happened.
Common mistakes
Selecting accident counts (A), which are the most common safety metric but are lagging, not leading.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert