    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 15
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 15 · Task 1: Plan and manage project compliance

    A project manager is classifying potential threats to compliance for a construction project in a historic city center. <br/><br/>Which TWO scenarios represent 'Environmental' compliance threats? (Select TWO)

    Answer options:

    A.

    Failure to pay overtime wages to construction workers

    B.

    Discovering archaeological artifacts during excavation

    C.

    Using software that has not been security patched

    D.

    Exceeding the budget for raw materials

    E.

    Noise levels exceeding city decibel limits during night shifts

    F.

    Lack of wheelchair ramps in the final design

    How to approach this question

    Identify issues related to the physical surroundings (Noise, Artifacts/Land).

    Full Answer

    B, E
    Environmental compliance covers impacts on the physical environment and community well-being. Noise pollution (E) and disturbing archaeological heritage (B) fall under environmental protection regulations in many jurisdictions. Wages (A) are labor law. Ramps (F) are accessibility.

    Common mistakes

    Thinking Environmental only means 'nature/trees'. It includes noise, dust, and heritage.
    Question 14All questionsQuestion 16

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard