PMP · Question 16 · Task 2: Evaluate and deliver project benefits and value
A project delivers a new CRM software (Output). The sales team uses the software to track leads more effectively (Outcome). As a result, revenue increases by 15% (Benefit).<br/><br/>Which of these should the project manager PRIMARILY track to demonstrate the project's success to the business stakeholders?
A project delivers a new CRM software (Output). The sales team uses the software to track leads more effectively (Outcome). As a result, revenue increases by 15% (Benefit).<br/><br/>Which of these should the project manager PRIMARILY track to demonstrate the project's success to the business stakeholders?
Answer options:
A.
The successful installation of the CRM software
B.
The number of sales team members trained
C.
The increase in revenue
D.
The completion of the project on time and on budget
How to approach this question
Distinguish between Output (Deliverable) and Benefit (Value). Business stakeholders care about Value.
Full Answer
C.The increase in revenue✓ Correct
C
While PMs track outputs (A) and schedule/cost (D), the Business Environment domain focuses on Value. The 'Benefit' (Revenue increase) is the ultimate measure of business success. The PM must align project goals with this value realization.
Common mistakes
Focusing on 'Iron Triangle' metrics (D) instead of Business Value (C).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert