PMP · Question 17 · Task 2: Evaluate and deliver project benefits and value
A project is nearing closure. The project manager is working to ensure that the benefits identified in the business case will be sustained after the project team disbands.<br/><br/>Which TWO actions are MOST critical for the project manager to take? (Select TWO)
A project is nearing closure. The project manager is working to ensure that the benefits identified in the business case will be sustained after the project team disbands.<br/><br/>Which TWO actions are MOST critical for the project manager to take? (Select TWO)
Answer options:
Extend the project timeline to monitor benefits for 12 months.
Confirm and document the owner responsible for ongoing benefits realization.
Write a final project report stating that all benefits have been achieved.
Verify that the measurement system is in place to track the benefits.
Transfer the remaining project budget to the operations team.
Archive the benefits management plan without updating it.
How to approach this question
Full Answer
Common mistakes
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
Expert