    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 23
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valueBusiness EnvironmentValueTask 2

    PMP · Question 23 · Task 2: Evaluate and deliver project benefits and value

    A project manager is establishing a measurement system to track the benefits of a new marketing campaign project. The goal is to increase brand awareness.<br/><br/>Which TWO actions should the project manager take to ensure the measurement system is effective? (Select TWO)

    Answer options:

    A.

    Wait until the project is finished to decide on metrics.

    B.

    Select metrics that are easy to measure, even if they are not directly related to the goal.

    C.

    Establish a baseline of current brand awareness before the project starts.

    D.

    Agree on the specific metrics (e.g., social media mentions, survey results) with the stakeholders.

    E.

    Assign the project team to manually count brand mentions indefinitely.

    F.

    Use the same metrics as the previous engineering project.

    How to approach this question

    To measure change, you need a Baseline (Start) and agreed Metrics (Ruler).

    Full Answer

    C, D
    Effective measurement requires a baseline (C) to compare against and agreement on what to measure (D). Without a baseline, you can't prove improvement. Without agreement, stakeholders may dispute the results.

    Common mistakes

    Selecting A (waiting) or B (easy metrics).
    Question 22All questionsQuestion 24

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard