For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 24
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valueBusiness EnvironmentValueTask 2

    PMP · Question 24 · Task 2: Evaluate and deliver project benefits and value

    A project to automate a factory line will increase production speed by 50% (Benefit). However, it will also result in the layoff of 20 employees, which will negatively impact the company's reputation in the local community.<br/><br/>What is the term for this negative impact?

    Answer options:

    A.

    Dis-benefit

    B.

    Sunk cost

    C.

    Opportunity cost

    D.

    Risk trigger

    How to approach this question

    Identify the definition. Negative side effect = Dis-benefit.

    Full Answer

    A.Dis-benefit✓ Correct
    A dis-benefit is a negative impact that results from a project. While the project delivers value (speed), it also causes harm (layoffs/reputation). PMs must account for dis-benefits in the business case.

    Common mistakes

    Confusing dis-benefit with risk (which is uncertain; this seems to be a certain consequence).
    Question 23All questionsQuestion 25

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →