PMP · Question 27 · Task 2: Evaluate and deliver project benefits and value
A project manager is closing a project that implemented a new employee training portal. The benefits management plan states that the primary benefit is 'Improved Employee Retention'.<br/><br/>When should this benefit be measured?
Answer options:
During the project execution phase.
Immediately at project closure.
Well after project closure, as defined in the benefits management plan.
It cannot be measured quantitatively.