Hard1 markMultiple Choice
PMP · Question 27 · Task 2: Evaluate and deliver project benefits and value
A project manager is closing a project that implemented a new employee training portal. The benefits management plan states that the primary benefit is 'Improved Employee Retention'.<br/><br/>When should this benefit be measured?
A project manager is closing a project that implemented a new employee training portal. The benefits management plan states that the primary benefit is 'Improved Employee Retention'.<br/><br/>When should this benefit be measured?
Answer options:
A.
During the project execution phase.
B.
Immediately at project closure.
C.
Well after project closure, as defined in the benefits management plan.
D.
It cannot be measured quantitatively.
How to approach this question
Understand the timeline of benefits. Strategic benefits usually lag behind project closure.
Full Answer
C.Well after project closure, as defined in the benefits management plan.✓ Correct
C
Benefits realization often occurs after the project is closed and the deliverables are being used in operations. Employee retention is a long-term metric.
Common mistakes
Thinking all project work/measurement ends at closure (B).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert