Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3
PMP · Question 31 · Task 3: Evaluate and address external business environment changes
A multinational corporation is planning a project to expand into a new country. The project manager performs a PESTLE analysis and identifies that the target country has recently increased tariffs on imported technology hardware.<br/><br/>Which PESTLE factor does this represent?
A multinational corporation is planning a project to expand into a new country. The project manager performs a PESTLE analysis and identifies that the target country has recently increased tariffs on imported technology hardware.<br/><br/>Which PESTLE factor does this represent?
Answer options:
A.
Social
B.
Technological
C.
Economic
D.
Environmental
How to approach this question
Tariffs = Money/Cost = Economic. (Note: Political is also a strong contender, but usually Tariffs are categorized under Economic in PMP exams unless 'Trade War' is specified). If Political was an option and Economic wasn't, choose Political. If both, Economic is often preferred for 'Tariffs/Taxes'.
Full Answer
C.Economic✓ Correct
C
Tariffs directly impact the cost of doing business and are a financial lever, making them an Economic factor. (They are politically motivated, but the factor itself—a tax/cost—is economic).
Common mistakes
Confusing with Technological because it involves 'hardware'.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert