A project manager is reviewing the project charter. The charter states the project's goal is to 'Improve Customer Satisfaction'. However, the project scope only includes 'Upgrading the Server Hardware'.<br/><br/>What is the misalignment here?
A project manager is reviewing the project charter. The charter states the project's goal is to 'Improve Customer Satisfaction'. However, the project scope only includes 'Upgrading the Server Hardware'.<br/><br/>What is the misalignment here?
Answer options:
A.
There is no misalignment; faster servers always improve satisfaction.
B.
The project scope (Output) may not directly lead to the strategic goal (Outcome).
C.
The charter should not contain strategic goals.
D.
The scope is too broad.
How to approach this question
Look for the link between 'What we are building' and 'Why we are building it'. If the link is weak, that's the risk.
Full Answer
B.The project scope (Output) may not directly lead to the strategic goal (Outcome).✓ Correct
This is a classic Business Environment issue: Alignment. The PM must ensure the project deliverables actually support the strategic intent. Upgrading hardware (Output) might not improve satisfaction (Outcome) if the real issue is software usability or support service.
Common mistakes
Assuming technical improvements automatically equal business value (A).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard