Hard1 markMultiple Choice
Task 2: Evaluate and deliver project benefits and valueBusiness EnvironmentValueTask 2Matching Conversion
PMP · Question 29 · Task 2: Evaluate and deliver project benefits and value
A project manager is evaluating delivery options to demonstrate value. The organization needs to see a return on investment as quickly as possible to fund future phases.<br/><br/>Which delivery approach is BEST suited for this need?
A project manager is evaluating delivery options to demonstrate value. The organization needs to see a return on investment as quickly as possible to fund future phases.<br/><br/>Which delivery approach is BEST suited for this need?
Answer options:
A.
Predictive (Waterfall) with a single final release
B.
Big Bang delivery
C.
Incremental delivery
D.
Parallel delivery of all components
How to approach this question
Match the need (Speed of Value) to the Approach. Incremental = Early Value.
Full Answer
C.Incremental delivery✓ Correct
Incremental delivery provides usable deliverables at the end of each iteration/increment. This allows the organization to realize value (and potentially revenue) earlier than a predictive/big-bang approach which delivers everything at the end.
Common mistakes
Confusing 'Iterative' (refining) with 'Incremental' (delivering pieces). Incremental is key for early value.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard