Hard1 markMultiple Choice
Task 2: Evaluate and deliver project benefits and valueBusiness EnvironmentValueTask 2Matching Conversion

PMP · Question 29 · Task 2: Evaluate and deliver project benefits and value

A project manager is evaluating delivery options to demonstrate value. The organization needs to see a return on investment as quickly as possible to fund future phases.<br/><br/>Which delivery approach is BEST suited for this need?

Answer options:

A.

Predictive (Waterfall) with a single final release

B.

Big Bang delivery

C.

Incremental delivery

D.

Parallel delivery of all components

How to approach this question

Match the need (Speed of Value) to the Approach. Incremental = Early Value.

Full Answer

C.Incremental delivery✓ Correct
Incremental delivery provides usable deliverables at the end of each iteration/increment. This allows the organization to realize value (and potentially revenue) earlier than a predictive/big-bang approach which delivers everything at the end.

Common mistakes

Confusing 'Iterative' (refining) with 'Incremental' (delivering pieces). Incremental is key for early value.