Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3

PMP · Question 41 · Task 3: Evaluate and address external business environment changes

How frequently should a project manager review the external business environment for impacts on the project scope?

Answer options:

A.

Only during the initiation phase.

B.

Only when a risk is triggered.

C.

Continually throughout the project lifecycle.

D.

Only at the end of each phase.

How to approach this question

Best Practice: Monitoring is Continuous.

Full Answer

C.Continually throughout the project lifecycle.✓ Correct
C
The business environment is dynamic. The PM must 'Continually review' (Task 3 Enabler) to ensure the project remains aligned. Waiting for phases (D) or risks (B) leaves the project vulnerable.

Common mistakes

Thinking it's a one-time planning activity (A).

Practice the full PMP Business Environment Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam