Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3
PMP · Question 41 · Task 3: Evaluate and address external business environment changes
How frequently should a project manager review the external business environment for impacts on the project scope?
How frequently should a project manager review the external business environment for impacts on the project scope?
Answer options:
A.
Only during the initiation phase.
B.
Only when a risk is triggered.
C.
Continually throughout the project lifecycle.
D.
Only at the end of each phase.
How to approach this question
Best Practice: Monitoring is Continuous.
Full Answer
C.Continually throughout the project lifecycle.✓ Correct
C
The business environment is dynamic. The PM must 'Continually review' (Task 3 Enabler) to ensure the project remains aligned. Waiting for phases (D) or risks (B) leaves the project vulnerable.
Common mistakes
Thinking it's a one-time planning activity (A).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert