PMP · Question 42 · Task 3: Evaluate and address external business environment changes
A project manager is leading a project to develop a fossil-fuel based power plant. A global climate summit results in a new international treaty aiming to phase out such plants within 5 years. The project is scheduled to last 4 years.<br/><br/>What is the MOST strategic recommendation the project manager should make to the steering committee?
Answer options:
Accelerate the schedule to finish in 3 years.
Re-evaluate the project's long-term viability and consider termination or repurposing.
Ignore the treaty as it is not yet local law.
Reduce the project scope to save money.