    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 42
    Hard1 markMultiple Choice
    Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3

    PMP · Question 42 · Task 3: Evaluate and address external business environment changes

    A project manager is leading a project to develop a fossil-fuel based power plant. A global climate summit results in a new international treaty aiming to phase out such plants within 5 years. The project is scheduled to last 4 years.<br/><br/>What is the MOST strategic recommendation the project manager should make to the steering committee?

    Answer options:

    A.

    Accelerate the schedule to finish in 3 years.

    B.

    Re-evaluate the project's long-term viability and consider termination or repurposing.

    C.

    Ignore the treaty as it is not yet local law.

    D.

    Reduce the project scope to save money.

    How to approach this question

    Strategic Alignment. If the future makes the product worthless, stop/change now.

    Full Answer

    B.Re-evaluate the project's long-term viability and consider termination or repurposing.✓ Correct
    B
    The external environment (Legal/Social) has signaled that the project's output will have a very short useful life. Strategic alignment requires re-evaluating the business case. Building it anyway (A) is poor stewardship of organizational resources.

    Common mistakes

    Focusing on 'getting it done' (A) rather than 'is it worth doing' (B).
    Question 41All questionsQuestion 43

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →