Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3Procurement
PMP · Question 43 · Task 3: Evaluate and address external business environment changes
A project manager observes that the inflation rate has increased significantly, raising the cost of raw materials. The project is a fixed-price contract with a client.<br/><br/>Who bears the risk of this external environmental change?
A project manager observes that the inflation rate has increased significantly, raising the cost of raw materials. The project is a fixed-price contract with a client.<br/><br/>Who bears the risk of this external environmental change?
Answer options:
A.
The Seller (Project Team/Organization)
B.
The Buyer (Client)
C.
Both parties equally
D.
The Government
How to approach this question
Contract Theory. Fixed Price = Seller Risk. Cost Reimbursable = Buyer Risk.
Full Answer
A.The Seller (Project Team/Organization)✓ Correct
A
Economic factors (Inflation) impact contracts differently. In a Fixed Price contract, the seller is obligated to deliver at the agreed price, regardless of their own cost increases. Thus, the seller bears the risk of inflation.
Common mistakes
Thinking risks are always shared.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert