    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 47
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

    PMP · Question 47 · Task 4: Support organizational change

    A project will introduce a new timesheet system that requires employees to log tasks in 15-minute intervals. The project manager anticipates significant resistance from the staff.<br/><br/>Which TWO actions should the project manager take to support this organizational change? (Select TWO)

    Answer options:

    A.

    Implement the system secretly and announce it only when live.

    B.

    Communicate the 'Why' (benefits) of the change to all stakeholders early.

    C.

    Threaten disciplinary action for non-compliance.

    D.

    Ignore the resistance and rely on the sponsor to force the change.

    E.

    Identify and empower 'Change Champions' within the staff to advocate for the system.

    F.

    Increase the complexity of the system to capture more data.

    How to approach this question

    Change Management = Communication + Engagement. Look for 'Soft Skills' answers.

    Full Answer

    B, E
    To support organizational change, the PM should use Change Management principles. Communicating the vision/benefits (B) and using Change Champions (E) are proven methods to reduce resistance. Secrecy (A) and threats (C) fail.

    Common mistakes

    Resorting to force (C) or authority (D).
    Question 46All questionsQuestion 48

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →