Hard1 markMultiple Choice
PMP · Question 60 · Task 4: Support organizational change
Before implementing a project that will automate 50% of the workforce's tasks, the project manager conducts a 'Readiness Assessment'.<br/><br/>What is the PRIMARY purpose of this assessment?
Before implementing a project that will automate 50% of the workforce's tasks, the project manager conducts a 'Readiness Assessment'.<br/><br/>What is the PRIMARY purpose of this assessment?
Answer options:
A.
To identify which employees to fire.
B.
To test the software for bugs.
C.
To measure the organization's ability and willingness to adapt to the change.
D.
To calculate the ROI of the project.
How to approach this question
Readiness = Ability + Willingness.
Full Answer
C.To measure the organization's ability and willingness to adapt to the change.✓ Correct
A Readiness Assessment evaluates the gap between the current state and the future state, focusing on culture, skills, and willingness. It informs the Change Management Plan.
Common mistakes
Confusing with technical readiness (B).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard