Hard1 markMultiple Choice
Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

PMP · Question 60 · Task 4: Support organizational change

Before implementing a project that will automate 50% of the workforce's tasks, the project manager conducts a 'Readiness Assessment'.<br/><br/>What is the PRIMARY purpose of this assessment?

Answer options:

A.

To identify which employees to fire.

B.

To test the software for bugs.

C.

To measure the organization's ability and willingness to adapt to the change.

D.

To calculate the ROI of the project.

How to approach this question

Readiness = Ability + Willingness.

Full Answer

C.To measure the organization's ability and willingness to adapt to the change.✓ Correct
A Readiness Assessment evaluates the gap between the current state and the future state, focusing on culture, skills, and willingness. It informs the Change Management Plan.

Common mistakes

Confusing with technical readiness (B).