PMP · Question 59 · Task 4: Support organizational change
A project manager is categorizing stakeholder resistance. One stakeholder agrees with the change in public but delays deliverables and spreads rumors in private.<br/><br/>What type of resistance is this?
Answer options:
Active Resistance
Passive Resistance
Constructive Resistance
Unconscious Resistance