Hard1 markMultiple Choice
PMP · Question 59 · Task 4: Support organizational change
A project manager is categorizing stakeholder resistance. One stakeholder agrees with the change in public but delays deliverables and spreads rumors in private.<br/><br/>What type of resistance is this?
A project manager is categorizing stakeholder resistance. One stakeholder agrees with the change in public but delays deliverables and spreads rumors in private.<br/><br/>What type of resistance is this?
Answer options:
A.
Active Resistance
B.
Passive Resistance
C.
Constructive Resistance
D.
Unconscious Resistance
How to approach this question
Hidden/Quiet blocking = Passive.
Full Answer
B.Passive Resistance✓ Correct
B
Passive resistance is the most dangerous because it is hidden. It involves agreeing on the surface but undermining the effort behind the scenes.
Common mistakes
Thinking resistance is always loud (Active).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert