PMP · Question 58 · Task 4: Support organizational change

The organization has undergone three major restructurings in the last two years. The project manager notices that stakeholders are apathetic and disengaged from the new project's change initiatives.<br/><br/>What is this phenomenon called?

Answer options:

A.

Scope Creep

B.

Analysis Paralysis

C.

Change Fatigue

D.

Groupthink

How to approach this question

Too much change -> Apathy = Change Fatigue.

Full Answer

C.Change Fatigue✓ Correct
Change Fatigue occurs when an organization faces too much change in a short period. Stakeholders become passive and resistant. The PM must recognize this and adjust the pace or support level.

Common mistakes

Confusing with general resistance.