    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 57
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

    PMP · Question 57 · Task 4: Support organizational change

    Who is ULTIMATELY responsible for championing the organizational change brought about by the project and removing high-level political roadblocks?

    Answer options:

    A.

    The Project Manager

    B.

    The Project Sponsor

    C.

    The Project Team

    D.

    The Functional Manager

    How to approach this question

    Sponsor = Champion/Political Cover/Money.

    Full Answer

    B.The Project Sponsor✓ Correct
    B
    While the PM supports change, the Project Sponsor is accountable for enabling the change at the executive level and removing political barriers.

    Common mistakes

    Thinking the PM has to do everything. The PM escalates political blocks to the Sponsor.
    Question 56All questionsQuestion 58

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →