    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 56
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

    PMP · Question 56 · Task 4: Support organizational change

    A project involves implementing a new ERP system. The project manager identifies that the finance team lacks the digital literacy required to use the new system.<br/><br/>What should the project manager do to address this organizational impact?

    Answer options:

    A.

    Simplify the system to match current skills.

    B.

    Request that HR hire new finance staff.

    C.

    Include a comprehensive training and upskilling program in the project scope.

    D.

    Launch the system and let them learn on the job.

    How to approach this question

    Gap in capability -> Training/Upskilling.

    Full Answer

    C.Include a comprehensive training and upskilling program in the project scope.✓ Correct
    When a project impacts the organization (requires new skills), the PM must plan for the necessary actions to enable adoption. Training (C) is the standard response to a skills gap.

    Common mistakes

    Assuming training is outside project scope (it is often part of transition).
    Question 55All questionsQuestion 57

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →