PMP · Question 56 · Task 4: Support organizational change
A project involves implementing a new ERP system. The project manager identifies that the finance team lacks the digital literacy required to use the new system.<br/><br/>What should the project manager do to address this organizational impact?
Answer options:
Simplify the system to match current skills.
Request that HR hire new finance staff.
Include a comprehensive training and upskilling program in the project scope.
Launch the system and let them learn on the job.