Hard1 markMultiple Choice
PMP · Question 56 · Task 4: Support organizational change
A project involves implementing a new ERP system. The project manager identifies that the finance team lacks the digital literacy required to use the new system.<br/><br/>What should the project manager do to address this organizational impact?
A project involves implementing a new ERP system. The project manager identifies that the finance team lacks the digital literacy required to use the new system.<br/><br/>What should the project manager do to address this organizational impact?
Answer options:
A.
Simplify the system to match current skills.
B.
Request that HR hire new finance staff.
C.
Include a comprehensive training and upskilling program in the project scope.
D.
Launch the system and let them learn on the job.
How to approach this question
Gap in capability -> Training/Upskilling.
Full Answer
C.Include a comprehensive training and upskilling program in the project scope.✓ Correct
C
When a project impacts the organization (requires new skills), the PM must plan for the necessary actions to enable adoption. Training (C) is the standard response to a skills gap.
Common mistakes
Assuming training is outside project scope (it is often part of transition).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard