Hard1 markMultiple Choice
Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

PMP · Question 56 · Task 4: Support organizational change

A project involves implementing a new ERP system. The project manager identifies that the finance team lacks the digital literacy required to use the new system.<br/><br/>What should the project manager do to address this organizational impact?

Answer options:

A.

Simplify the system to match current skills.

B.

Request that HR hire new finance staff.

C.

Include a comprehensive training and upskilling program in the project scope.

D.

Launch the system and let them learn on the job.

How to approach this question

Gap in capability -> Training/Upskilling.

Full Answer

C.Include a comprehensive training and upskilling program in the project scope.✓ Correct
C
When a project impacts the organization (requires new skills), the PM must plan for the necessary actions to enable adoption. Training (C) is the standard response to a skills gap.

Common mistakes

Assuming training is outside project scope (it is often part of transition).