    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 02
    Hard1 markMultiple Choice
    Task 2: Lead a teamPeopleLeadershipAgile

    PMP · Question 02 · Task 2: Lead a team

    A project manager has taken over a project where the team morale is low. Team members feel their suggestions are ignored by the previous manager and they lack autonomy. The project is using a predictive approach, but the organization is shifting toward agile. What is the BEST leadership style for the project manager to adopt to improve performance?

    Answer options:

    A.

    Directive Leadership

    B.

    Laissez-faire Leadership

    C.

    Transactional Leadership

    D.

    Servant Leadership

    How to approach this question

    Analyze the team's specific pain points (ignored, lack of autonomy) and match them to the leadership style that prioritizes team growth and empowerment.

    Full Answer

    D.Servant Leadership✓ Correct
    Servant leadership is the preferred style in modern project management, especially when transitioning to agile, as it empowers teams and rebuilds trust.

    Common mistakes

    Confusing Laissez-faire (hands-off) with Servant Leadership (hands-on support).
    Question 01All questionsQuestion 03

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...HardQ06A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. Th...Hard
    View all 20 questions →