Hard1 markMultiple Choice
PMP · Question 05 · Task 8: Negotiate project agreements
During a negotiation with a vendor for a critical component, the vendor states they cannot meet the required delivery date due to supply chain issues. This component is on the critical path. The vendor offers a 10% discount if the deadline is extended by two weeks. What is the BEST course of action for the project manager?
During a negotiation with a vendor for a critical component, the vendor states they cannot meet the required delivery date due to supply chain issues. This component is on the critical path. The vendor offers a 10% discount if the deadline is extended by two weeks. What is the BEST course of action for the project manager?
Answer options:
A.
Accept the discount and update the schedule baseline immediately.
B.
Demand the vendor meet the original date or face penalties.
C.
Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.
D.
Look for an alternative vendor who can meet the date.
How to approach this question
Always 'Analyze' or 'Assess' before acting. Never accept a change to the critical path without understanding the impact.
Full Answer
C.Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.✓ Correct
Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.
A delay on the critical path extends the project end date. The PM must calculate if the 10% discount covers the cost of project delay (e.g., penalties, lost revenue).
Common mistakes
Assuming the discount is worth it or immediately fighting the vendor without data.
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ06A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. Th...Hard
Expert