Hard1 markShort Answer

PMP · Question 06 · Task 5: Plan and manage budget and resources

A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000 and the Earned Value (EV) is $40,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols or commas).

How to approach this question

Calculate CPI first, then use the formula EAC = BAC / CPI.

Full Answer

112500
CPI = 40,000 / 45,000 = 0.8888... <br/>EAC = 100,000 / 0.8888... = 112,500.

Common mistakes

Using the wrong EAC formula (e.g., AC + ETC) when the prompt specifies 'current variances are typical'.

Practice the full PMI PMP Mini Practice Exam 2

20 questions · hints · full answers · grading

More questions from this exam